Solving Single Machine Bi-Criteria and Bi-Objectives Scheduling Problems of Total Tardiness and Range of Lateness Using Exact and Local Search Methods
DOI:
https://doi.org/10.70882/cs3q7a13Keywords:
Machine scheduling problem (MSP), Total tardiness, Range of lateness, Branch and Bound Method, Complete Enumeration MethodAbstract
In manufacturing and production planning environments, where efficiency depends on optimizing time-based performance measures, scheduling operations on a single machine is a foundational challenge. This study examines a single-machine scheduling problem (MSP) focusing on minimizing the total tardiness of jobs and the range of late jobs as evaluation criteria. The problem is formulated in two ways: a bi-criteria model and a bi-objective model each of them is NP-hard problem. In theoretical part: Several special cases of these formulations are analyzed to better understand their characteristics. Some cases were provided that lead to the optimal solution, and others led to efficient solutions. While in practical part: To obtain effective solutions, local search methods such as the Artificial Bee Colony algorithm and Tabu Search are proposed and applied. In addition, some exact and modified solution techniques are used to solve the problems and verify the obtained results. Computational experiments demonstrate the efficiency and accuracy of the proposed approaches in solving both scheduling models.
Downloads
Downloads
Published
Issue
Section
License
Copyright (c) 2026 Journal of Pure and Applied Sciences (Science Forum)

This work is licensed under a Creative Commons Attribution-NonCommercial-ShareAlike 4.0 International License.